Current Progress
(as of Nov. 10/08) Structural steel erection is complete. All concrete slabs have been poured with the exception of the roof level. Curtain wall installation is underway on level 17. Exterior stone installation has commenced on level 11. M&E rough ins continue on levels 15 - 21. Suites on levels 11 and 12 have been turned over to the Owner's fitout contractor. Project Description